Construction Update April 2026
What’s Happening on Site?
Internal Works
- Cut‑outs in the sports hall slab for the new piles have now been fully completed.


- Piling works for the new mezzanine structure foundations are ongoing within the sports hall.
- Screed removal has commenced in the new entrance area along with slab cut‑outs to allow installation of the new under‑slab drainage.


- Decoration works have begun to the underside of the exposed roof within the new entrance zone.
- From week commencing 20/04/26, a coordinated set of works will begin to create the new Dry Changing facilities on the ground floor. The initial works will include:
- Installation of temporary hoardings.
- Break‑out of the slab in the existing gym corridor for new drainage connections.
- Formation of the new drainage connection linking to existing systems.
Further information regarding temporary changes to the Citadel gym access route during this time can be found here – Notice: Temporary Gym Access – Citadel Leisure Redevelopment
External & Structural Works
- External scaffolds have been erected to facilitate façade removal works.
- Initial works to support future façade removal and wall opening formation are now underway.

Looking Ahead
- Pile‑cap construction is beginning, marking the next major phase in strengthening the building’s new layout.
- New structural openings are being formed within the existing sports hall walls to support future internal reconfiguration.
- The existing façade area is being removed, enabling the creation of a new, improved entrance into the gym space.
- Under‑slab drainage works are progressing in the new entrance area, preparing essential infrastructure for the upgraded facility.